Weekly Field Report

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

 

City of Sunset Valley
Public Works Department
Construction Weekly Field Report

 

 

 

Project: Combined 2022-2023 CIP

 

Date: 09/11/2023

 

Current Job Status

 

Scope Completed: Week of 9/4/2023

  • Water line installation on Sunset Trail is complete. Construction of the water line from Lone Oak Trail to Curley Mesquite Cove is complete. Construction of the turnaround on Lone Oak Trail complete.  Water line on the North Side of Lone Oak is complete. Construction of the wastewater main on Hwy 290 is 75 percent complete. Construction of the water line for AISD meter conversion is complete. Construction of the back flow on Oakdale is complete. Mill and overlay on Sunset Trail and Lone Oak Trail is complete.

     

    Next Steps: Week of 9/11/2023

  • No scope planed, waiting on subcontractor.

 

Notes

  • Change order pending for fire hydrants (see 4/17/2023 report)
  • Weather has been a factor in slowing down construction
  • Contractor is waiting on subcontractor to finish Hwy 290 Wastewater Main

Project Contingency

Project Contingency Budget

Pending Contingency Expense

Description

Remaining Budget

$190,070

$6,000

Change Order #1 American Darling Hydrants

$184,070

$14,203

Soil Testing

$169,867